Bhubaneswar: The Housing & Urban Development Department, Government of Odisha, has made significant progress in restoration and relief operations in the aftermath of Cyclone Arnab, with substantial improvements in water supply, public health engineering services and delivery of essential relief to affected people across Berhampur, Ganjam, Gajapati and other affected Urban Local Bodies (ULBs). The consolidated status report, as of 5:00 PM on November 2, 2026, highlights the continued efforts of the Department and field-level agencies to restore normalcy on a priority basis.
In Berhampur, water supply has improved to 72 MLD against the daily demand of 90 MLD. Of this, 64 MLD is being supplied through surface water sources, while 8 MLD is being generated from 18 operational production wells. Water supply to critical institutions, including MKCG Medical College and Hospital and IISER, has been fully restored. Distribution in Hinjilicut and Gopalpur is also continuing smoothly. To meet immediate requirements in affected localities, 46 water tankers, including 12 private tankers, have been deployed. Public health safety measures have been strengthened through super-chlorination at treatment plants. A Mobile Treatment Unit has also arrived at the Berhampur Division Office to support emergency water treatment requirements.
Meanwhile, restoration work at the washed-away Janivili Anicut is progressing on a war footing, with temporary ponding and sand bandh operations nearing 99 per cent completion. Around 200 labourers, five poclain machines and two tractors have been engaged in the operation. An ODRAF team has also been deployed to ensure the safety of workers engaged in the challenging restoration work. Approximately 15,000 sandbags have already been placed, with another 5,000 scheduled for placement. In addition, 20 workers have been stationed at the Janibilli Reservoir to support the ongoing operations.
At the state level, the Public Health Engineering Organisation (PHEO) has reported that water supply has been fully restored in 78 out of 86 ULBs across 10 Public Health Divisions. Overall restoration has reached approximately 98.73 per cent, with the current water supply standing at 445.74 MLD. Minor disruptions continue in eight ULBs under the Bhanjanagar Public Health Division, including Aska, Purusottampur and Chatrapur. Local production wells, hired water tankers and dedicated repair teams have been deployed to address the remaining issues and restore normal supply at the earliest.
Relief and municipal support measures have also been significantly strengthened. Additional officials and resources have been mobilised to support affected areas, including the deployment of five specialised engineers to oversee flood management and relief operations in Berhampur. Dry ration kits have been distributed to 1,800 families, while hot cooked meals are being served to around 650 people daily through 12 relief centres. All 24 temporary cyclone shelters continue to remain functional, providing essential support to affected people.
In Aska, targeted relief and recovery measures include the distribution of 20,000 candles and matchboxes to support affected households. Around 150 sanitation workers have also been deployed to undertake extensive cleaning and post-cyclone sanitation operations.
The Berhampur Municipal Corporation’s 24×7 Emergency Control Room, operational since October 25, 2026, continues to coordinate emergency response and address citizens’ grievances. So far, it has received and processed 341 public grievances. Citizens requiring assistance or wishing to report any issues can contact the control room through the dedicated helplines: 7608880480 and 0680-2250615.
The Housing & Urban Development Department continues to coordinate with concerned agencies and Urban Local Bodies to expedite restoration, ensure uninterrupted essential services and provide timely relief to affected communities. Allu field-level teams remain engaged in round-the-clock efforts to bring the affected areas back to normalcy.